Wall-mounted 7.4 kW electric vehicle chargers installed at residential site in Surrey for Zest


Project summary

We delivered the design and installation of new electric vehicle charging equipment at Banstead Wood, Surrey. This was a full turnkey project, including independent connection provider (ICP) works and NICEIC-certified installation.

Key deliverables

  • Installation of feeder pillar
  • Cable tray installation
  • Installation and commissioning of five Garo 7.4 kW wall-mounted chargers
  • Excavation of trench for ducting
  • New 69 kVA connection derived from the low-voltage network

Project details

Client: Zest