Electrical design and installation of low-voltage intake cables from 11 kV substation at Bovingdon Airfield Studios, Hertfordshire
Project summary
We completed the design, supply and installation of low-voltage intake cables from an existing 11 kV substation.
Key deliverables
- Low-voltage design for cables from stage B, C and D package substations (1250–1500 kVA) to the client’s low-voltage panel
- Supply and installation of low-voltage cables from stage B, C and D to low-voltage intake rooms adjacent to existing substations
- Completion of all cable terminations
- Low-voltage cable testing and energisation to the client’s air circuit breaker
Project details
Client: Bovingdon Studios

“Utility Line provide a personable, quick solution meeting all deadlines and budget requirements. The technical and civil engineering teams are extremely good at overcoming any obstacle, proving invaluable in challenging environments. The level of support and customer care exceeded our expectations, and we look forward to working with them in the future.”
Kirstie Evans
Operations Manager at Bovingdon Airfield Studios
Other projects
ProjectsInfrastructure design and installation of 150+ chargers for large-scale electric vehicle charging hub at the NEC Campus, Birmingham for The EV Network
ProjectsLow-voltage infrastructure design and installation for new EV charger at Windsor Marina for Aqua superPower
ProjectsLow-voltage connection and feeder pillar installation to feed new EV charger at Merry Hill, West Midlands for Zest
ProjectsNationwide maintenance and rapid response package covering 18 sites and 93 high-power charge points
Maximise the performance of your grid connections and electrical infrastructure
We help you navigate complex connection requirements, optimise network capacity, and extend the life of your electrical assets.
Contact our experts