We completed the design, supply and installation of low-voltage intake cables from an existing 11 kV substation.

Key deliverables

  • Low-voltage design for cables from stage B, C and D package substations (1250–1500 kVA) to the client’s low-voltage panel
  • Supply and installation of low-voltage cables from stage B, C and D to low-voltage intake rooms adjacent to existing substations
  • Completion of all cable terminations
  • Low-voltage cable testing and energisation to the client’s air circuit breaker

Project details

Client: Bovingdon Studios

Bovingdon Airfield Studios

1 of 1
Utility Line provide a personable, quick solution meeting all deadlines and budget requirements. The technical and civil engineering teams are extremely good at overcoming any obstacle, proving invaluable in challenging environments. The level of support and customer care exceeded our expectations, and we look forward to working with them in the future.

Kirstie Evans

Operations Manager at Bovingdon Airfield Studios

Maximise the performance of your grid connections and electrical infrastructure

We help you navigate complex connection requirements, optimise network capacity, and extend the life of your electrical assets.